How long does steel fabrication take?

October 10, 2026  ·  Indumor

Steel structure project planning

"When can I have it?" is the second question in every RFQ (price is the first). The honest answer: it depends on stages you do not all see. Here is the real timeline of a typical project at Indumor, so you know what to expect and what you can accelerate yourself.

Stage 1: engineering and detailing (3-10 days)

From the general arrangement to shop drawings: every piece with its dimensions, holes and welds. If your project arrives with detail engineering done, this stage almost disappears — which is why a good RFQ speeds up everything.

Stage 2: the steel (2-10 days)

Common plate and profiles ship from local stock in days. Large sections, special grades or specific stainless can take weeks. Tip: built-up girders are sometimes faster than waiting for an imported rolled section.

Stage 3: fabrication (1-4 weeks by tonnage)

Cutting, fit-up, welding, verification. A simple platform ships in days; a complete building package takes weeks. This is where the integrated plant makes the difference: no queues between subcontracted shops.

Stage 4: finishing (3-10 days)

Paint in our plant: days. Hot-dip galvanizing adds the galvanizer’s cycle (typically a week). It gets planned from day one, not at the end. For export clients, add packing and freight — we quote door-to-door times up front.

What delays a project (and how to avoid it)

  • Changes after fabrication starts: freeze the design before cutting.
  • Open definitions: anchors, finish and accessories get defined at the start.
  • Slow progress payments: steel is bought at kickoff; the deposit unlocks materials.

Our rule: the date we give with the quote is the date we hit — because every stage happens inside our own plant.

← Back to blog

Related services

Request a quote

With a committed delivery date.

View service →

How to RFQ

The info that accelerates your project.

View service →

Estimating weight

Budget before engineering exists.

View service →

Working against a deadline?

Tell us the date and we confirm feasibility before quoting.