Skid receiving checklist for the field

October 20, 2026  ·  Indumor

Piping, valves and actuators in a process plant

Who checks the skid when it arrives on site? If the answer is “whoever is around,” the skid can be well built and still start up badly. Ever since the oil industry made skids popular, more than half a century ago, the scene has repeated itself: the truck arrives, the crane sets it down, everyone looks at the clock and nobody looks at the anchors.

A skid is assembled and checked in the shop; the trip and the unloading are when something can change. This is the list worth having printed on the day it arrives:

  1. Documentation: as-built drawings, packing list and the quality documentation the project asked for.
  2. Transport damage: dents in the frame, damaged coating, flange covers in place and instruments intact.
  3. Lifting: only by the marked points, with the slings and spreader bar shown on the drawing. Never from a pipe.
  4. Anchors: base plate holes lining up with the foundation bolts before the skid is fully set down.
  5. Leveling: with the skid set, the equipment pads still level.
  6. Alignment: re-check pump-motor alignment after setting and anchoring; the trip and tightening the anchors can move it.
  7. Drains and drip pan: clean, clear and plugged.
  8. Loose parts: everything that shipped separately, checked against the packing list.
  9. Grounding: the frame bonded to the plant grounding grid before anything is energized.
  10. Touch-up: damaged coating or galvanizing repaired before corrosion starts.

Before it arrives

A good share of receiving happens days earlier. The crane has to lift the skid's weight at the radius it will actually work at, not the shortest one; the access road has to let the truck in and turn around; the foundation has to be cured, with the anchor bolts set to the template; and there has to be a sheltered spot for the parts that ship separately. If the skid is large, a written lift plan with the weight, the center of gravity and the rigging is worth having. Plus one named person holding the checklist.

After hook-up

When the plant piping is connected, check one more thing: that it meets the skid without forcing the flanges. A pipe that has to be pulled into place with a come-along passes that force on to the pump and misaligns it, even if alignment was measured correctly before hook-up.

None of these takes more than a few minutes, and together they prevent a lot of troubled start-ups. Alignment is the one most often forgotten and the one that costs most: a misalignment nobody measures gets paid for later in bearings and seals.

To see what a good skid should bring from the shop, read equipment skids: machinery on a steel frame and oil and gas skids; the piping that often comes installed is covered in shop-prefabricated piping. At Indumor we build equipment skids with machined pads, like our machine frames.

Have a skid on the way and still don't know who is going to receive it?

← Back to the Knowledge Hub

Keep reading

Equipment skids

Frames with machined pads.

View service →

Oil and gas skids

What to know before ordering one.

Read guide →

Have a skid to receive?

We will send you the checklist adapted to your equipment.