Truck scale foundation and ramps: drawings, approaches and which ramp to pick

November 24, 2026  ·  Indumor

Section of a pitless truck scale with the level approach (1), the ramp (2) ending in a first level section (P), the deck (3) resting on a pier or slab under each support (4) with its embedded plate (5), and the drainage slope running away from the scale (6)

1, level approach; 2, ramp; 3, deck; 4, pier or slab under each support; 5, embedded plate; 6, drainage slope; P, first level section.

The lowboy with the deck modules pulls onto the site, the crane is already parked alongside, and whoever is running the install pulls a tape between two embedded plates. The number doesn't match the drawing. Nobody did it on purpose. The contractor poured the piers off an old revision, or someone nudged a plate over a couple of inches to clear a rebar, and now a module weighing several tonnes is hanging off the sling while people argue on the phone about who has the latest version. In this trade it happens more often than anyone likes to admit, and when it does, the day is gone. Sometimes the whole week goes with it.

Most of what goes wrong under a truck scale can be fixed earlier, on paper. That's what this guide to weighbridge foundation and ramp design is about.

Two drawings that have to agree

A weighbridge comes with at least two sets of drawings. One covers the steel structure, meaning the modules, the load cell mounts, the ramps and the side rails. The other covers the foundation. The foundation is built by a civil contractor working from the scale company's drawing or an engineer's. We at Indumor supply the embedded plates and the support locations, so whoever pours knows where every plate goes before the first mixer truck shows up. If the scale company has its own deck drawings, we build to them, and the support locations come straight from there.

We build the steel structure. The load cells, the indicator and getting the scale set up and running come from the scale company, and we coordinate with them.

Before anyone pours, ask for a foundation drawing with a revision number and a date, and with every support dimensioned from one common origin. It sounds like nothing. It's exactly what heads off the lowboy-and-tape mess. Scale plates are close cousins of column base plates, and the care it takes to make the steel fit the first time is covered in anchor rods and column base plates.

What the technical standards ask of the foundation

The most concrete references come from North America. The US NIST Handbook 44 (2026 edition, section 2.20, paragraph UR.2.4) asks for a foundation and supports with strength, rigidity and permanence, and for enough clearance around the live parts that they don't touch under any load. The gap between the deck and the curb has to be wider at the bottom than at the top, so whatever drops into the joint can keep falling instead of wedging. A stone wedged in that joint is the most cited cause of bad weights, which we get into in truck scale maintenance.

The Measurement Canada field inspection manual wants the foundation or pit below the frost line or on stable ground, and accepts a reinforced floating slab. Under each support it wants clean, smooth steel shims that fill the whole void, or grout that fills it completely. One small shim in the middle of the plate with the rest in the air doesn't fit that description.

Manufacturer spec sheets get down to numbers. One from the US calls for soil bearing of 2,500 psf (about 120 kPa) under footings, 1,500 psf (72 kPa) under a slab with grade beams and 2,000 psf (96 kPa) in a pit, 3,000 psi concrete (20.7 MPa) at 28 days with 5 to 7 % entrained air, a foundation covering the full length and width of the deck, sitting above grade and draining away from the center, and at least 3 in (76 mm) of clearance between concrete and steel. Those 76 mm come from a commercial spec, not a standard. A brochure from India offers four foundation types (deep piers, shallow piers, pit and floating slab), and which one suits which ground is up to whoever signs the foundation drawing.

That leaves the number everybody asks for, the allowable level difference between plates. It's set by each scale company's foundation drawing. We found no public tolerance that holds for every scale, so you won't find a made-up one here.

Approaches, the stretch nobody looks at

The scale doesn't end where the deck plate ends. At the entry and the exit, Handbook 44 (UR.2.6.1) calls for a straight approach at least as wide as the deck and at least half the deck's length, without requiring more than 12 m (40 ft). The first 3 m (10 ft) next to the deck have to be in the same plane as the deck, and the rest sloped so as to make entry, testing and drainage away from the scale easier. If the scale stays in place for 6 months or more, those 3 m have to be concrete or another durable material, or a grating that carries the concentrated load capacity.

In real numbers, a 21 m deck needs 10.5 m of straight approach on each end, and a 24 m deck hits the 12 m cap. Measurement Canada counts an approach as "level" when the slope along it is no more than 2 % (2 cm per meter, about 1/4 in per foot) measured over at least 1 m, and any crown can't exceed 2 % either.

Steel ramp or concrete ramp

On a pitless scale the deck sits above grade. Catalogs put the deck surface somewhere between about 300 and 430 mm (12 to 17 in) above the foundation, and each end needs a ramp. A buying guide from a manufacturer in India sums it up in one line: the higher the deck, the longer the ramps and the more room you need to drive on straight. Under Handbook 44, the ramp ends in a flat section at deck height, marked P in the drawing. If you haven't settled on pit or pitless yet, that's covered in pit vs pitless truck scale.

 Steel rampConcrete ramp
Who builds itThe fab shop, along with the deckThe civil contractor, on site
If the scale movesLifts out and travels with the modulesStays where it was poured
On siteArrives finished, set down and fixedForming, pouring and waiting for the cure
3 m next to the deck (Handbook 44)Durable material or grating that carries the concentrated loadConcrete
What a buying guide recommends it forA scale that will be relocatedDurability

Ramps take the hit from every truck that climbs on, the same guide says. In one European catalog the steel ones come 3 m wide or as two 1 m wheel tracks.

Verdict. For a scale that's staying put at a plant, a grain elevator or a port, go with concrete approaches, poured by the contractor along with the foundation. For a road job, a quarry that keeps moving or a scale that's on one farm today and another in two years, go with steel ramps that lift out with the deck and travel with it. What to avoid is a makeshift steel ramp on a permanent site because it goes in faster. That's penny-wise and pound-foolish, since every truck hits the ramp first.

A pitless scale also takes side rails. One US spec calls for 4 in pipe at minimum, bolted on gussets with at least 3 bolts per gusset, and bans welding them to the deck structure. We build them with the deck, same as the ramps. As for installation, it depends on the site, so ask us how we'd handle yours.

Put in one line, a truck scale is only as good as the base and approaches it sits on, and that gets decided on the drawing before the first mixer arrives. If you're about to break ground, tell us where the scale goes and who's doing the civil work. We'll send the embedded plates and support locations for the contractor, and quote the truck scale steel structure with the ramps included.

Sources (manufacturer spec sheets are cited without links): NIST Handbook 44, 2026 edition, section 2.20 "Scales", paragraphs UR.2.4 and UR.2.6.1; Measurement Canada, Field Inspection Manual NAWDS, part 3, section 7; soil, concrete, 76 mm clearance and side rails from engineering specifications of US manufacturers; foundation types from a manufacturer's brochure in India; ramps from a buying guide from India and a European catalog; deck height from catalogs from Europe, the US and India.

← Back to the Knowledge Hub

Keep reading

Pit vs pitless

What changes on site and in the steel.

Read guide →

Anchor rods and base plates

Getting the steel to fit the first time.

Read guide →

Truck scale steel structures

Deck modules, ramps and side rails.

View service →

Is the foundation drawing ready?

Tell us where the scale goes and who is doing the civil work. We send the embedded plates and support locations, and a same-day quote for the steel.